Mesaimeer Pumping Station and Outfall

Brief description

​​Mesaimeer Pumping Station and Outfall is the second phase of the Mesaimeer Surface and Storm Water Drainage Tunnel Project which was completed in the late 2016. The project aims to achieve the objective of Mesaimeer Tunnel; discharging the surface and stormwater, thus decreasing the surface water level and reducing pumping costs in construction projects around the country. It will also preserve the foundations of buildings, and reduce land subsidence due to rain.

Benefits
The first part of the project is the outfall which is constructed with a length of ten kilometres from the seashore and is one of the longest outfall tunnels in the world, which ensures the preservation of the marine environment in the country.
At a depth of fifteen metres below the seabed, excavation of the outfall tunnel is a major construction challenge due to the changing land nature, the ground pressure and the water pressure at this depth. Therefore, excavation is done using the Tunnel Boring Maching (TBM) with “Earth Pressure Balance” technique, designed to operate in a range of ground conditions in Qatar. A highly professional and specialised team carries out all marine works.
The tunnel lining is conical universal precast concrete rings with a dimeter of around four metres, and is reinforced by steel fibres to protect the tunnel. The tunnel ends on a vertical riser shaft, which pushes storm water flows to a diffuser field with an area of  14,750 square metres.
The second part of the project consists of a pumping station with 10 pumps and auxiliary facilities. The pumping station will be located at the end of Mesaimeer Tunnel south of Hamad International Airport. The pumping station will operate at a capacity of 19.7 cubic metres per second, and its function is to pump water from Mesaimeer Tunnel to the new outfall tunnel.
Project Information
Geographical Location N/A
Area Multiple Areas
Sector Drainage Projects
Total Cost 920,000,000 Q.R.
Status In progress
Type Drainage
Start Date 26 November 2017
Expected completion date Fourth quarter of 2021
Construction company

JV of Hamad Bin Khalid Contracting Company and PORR Qatar Construction Company

Consulting company

Mott Macdonald Ltd